Notices, claims and time bars
How the Contract add-on counts the periods your contract sets, and what happens when one runs out.
Forms and registers
The registers are part of the Contract add-on. Choose the form in the contract set-up and the registers, the contract administrator’s title and the default rules follow from it.
The forms
- JBCC Principal Building Agreement (Principal Agent)
- GCC 2015 (Employer’s Agent)
- NEC3 Engineering and Construction Contract (Project Manager)
- NEC4 Engineering and Construction Contract (Project Manager)
- FIDIC 1999 (Red and Yellow Books) (Engineer)
- FIDIC 2017 (Red and Yellow Books) (Engineer)
- Other forms (a general set of rules to adjust)
The registers
Early warnings
Anything that could delay the works or add cost, raised early. Only for the forms that have an early warning procedure: not JBCC or GCC 2015.
Notices of delay
The formal notices that keep the right to claim more time.
Compensation events
Events at the employer’s risk that can change the price and the completion date.
EOT claims
Extension of time claims: the days asked for, the days granted and the revised completion date.
How a step is counted
Each step in a register counts from something that happened: becoming aware of the event, its start or end, or another step being taken or falling due. The period runs in the unit the contract uses, and the rule says what a missed step means.
| Unit | How it counts |
|---|---|
| Days | Calendar days, every day counted. |
| Working days | Days that work on the contract’s calendar, which defaults to the programme’s own. |
| Weeks | Calendar weeks of seven days. |
| Calendar days less holidays | Calendar days, skipping public holidays, proclaimed days and the builders’ break on the contract’s calendar. |
| Months | Calendar months, ending on the same date of the month, or the month’s last day when it is shorter. |
| Consequence | What it means |
|---|---|
| Time bar | The right is lost if the step is not taken in time. The register shows the entry as time-barred. |
| Deemed accepted | Silence counts as acceptance once the period runs out. The register shows the step as deemed. |
| Deemed refused | Silence counts as a refusal once the period runs out. |
| Reminder | Nothing is lost, but the step is shown as overdue so it can be chased. |
- A step shows as due soon 10 working days before its date by default; you can change that in the contract set-up.
- Steps that repeat, such as monthly interim claims while an event continues, are listed once for each period.
- Steps fall away when they no longer apply: a reminder to chase a reply once the reply is in, a dissatisfaction or dispute step once the claim is agreed.
- The deadlines of every register go out as an iCalendar file, for Outlook, Google or Apple calendars.
Default periods
When you choose one of these forms, Gantt CSS fills in its rules. The main rules are below. Each one is a starting point, editable per programme.
Check your contract. These are the defaults Gantt CSS starts from, and you can edit every one per programme. Contracts are often amended by special conditions, so check yours. This guide is not legal advice.
NEC3 Engineering and Construction Contract
Set up with early warnings and compensation events: notification, reply, quotation, and acceptance when the Project Manager does not reply.
| Step | Who | Period | Counted from | If missed | Clause noted |
|---|---|---|---|---|---|
| Early warning given | Contractor | Same day | Becoming aware of the matter | Reminder | 16.1 |
| Notify the compensation event | Contractor | 8 weeks | Becoming aware of the event | Time bar | 61.3 |
| Reply to the notification | Project Manager | 1 week | The notification | Reminder | 61.4 |
| Notification accepted if there is still no reply after the contractor points out the failure | Project Manager | 2 weeks | The contractor’s notice of the failure to reply | Deemed accepted | 61.4 |
| Submit the quotation | Contractor | 3 weeks | The reply to the notification | Reminder | 62.3 |
| Reply to the quotation | Project Manager | 2 weeks | The quotation | Reminder | 62.3 |
| Quotation accepted if there is still no reply after the contractor points out the failure | Project Manager | 2 weeks | The contractor’s notice of the failure to reply | Deemed accepted | 62.6 |
The defaults Gantt CSS starts from, editable per programme; check your contract.
NEC4 Engineering and Construction Contract
The same compensation event steps as NEC3, with the early warning under its own clause.
| Step | Who | Period | Counted from | If missed | Clause noted |
|---|---|---|---|---|---|
| Early warning given | Contractor | Same day | Becoming aware of the matter | Reminder | 15.1 |
| Notify the compensation event | Contractor | 8 weeks | Becoming aware of the event | Time bar | 61.3 |
| Reply to the notification | Project Manager | 1 week | The notification | Reminder | 61.4 |
| Notification accepted if there is still no reply after the contractor points out the failure | Project Manager | 2 weeks | The contractor’s notice of the failure to reply | Deemed accepted | 61.4 |
| Submit the quotation | Contractor | 3 weeks | The reply to the notification | Reminder | 62.3 |
| Reply to the quotation | Project Manager | 2 weeks | The quotation | Reminder | 62.3 |
| Quotation accepted if there is still no reply after the contractor points out the failure | Project Manager | 2 weeks | The contractor’s notice of the failure to reply | Deemed accepted | 62.6 |
The defaults Gantt CSS starts from, editable per programme; check your contract.
FIDIC 1999 (Red and Yellow Books)
Set up with a notice of probable future events, the notice of claim, the detailed claim with interim and final claims, and the Engineer’s response.
| Step | Who | Period | Counted from | If missed | Clause noted |
|---|---|---|---|---|---|
| Notice of claim | Contractor | 28 days | Becoming aware of the event | Time bar | 20.1 |
| Fully detailed claim (the first interim claim while the event continues) | Contractor | 42 days | Becoming aware of the event | Reminder | 20.1 |
| Further interim claims | Contractor | Every month | The detailed claim | Reminder | 20.1 |
| Final claim | Contractor | 28 days | The end of the event’s effects | Reminder | 20.1 |
| Engineer’s response | Engineer | 42 days | The detailed claim | Reminder | 20.1 |
The defaults Gantt CSS starts from, editable per programme; check your contract.
FIDIC 2017 (Red and Yellow Books)
Set up with advance warnings, the notice of claim, the detailed claim with interim and final claims, the Engineer’s agreement and determination, and a notice of dissatisfaction.
| Step | Who | Period | Counted from | If missed | Clause noted |
|---|---|---|---|---|---|
| Notice of claim | Contractor | 28 days | Becoming aware of the event | Time bar | 20.2.1 |
| Engineer says the notice was late, or it stands as valid | Engineer | 14 days | The notice of claim | Deemed accepted | 20.2.2 |
| Fully detailed claim (the first interim claim while the event continues) | Contractor | 84 days | Becoming aware of the event | Time bar | 20.2.4 |
| Further interim claims | Contractor | Every month | The detailed claim | Reminder | 20.2.6 |
| Final claim | Contractor | 28 days | The end of the event’s effects | Reminder | 20.2.6 |
| Engineer’s agreement | Engineer | 42 days | The detailed claim | Reminder | 3.7.3 |
| Engineer’s determination, or the claim counts as rejected | Engineer | 42 days | The end of the period for agreement | Deemed refused | 3.7.3 |
| Notice of dissatisfaction, if the claim is not agreed | Contractor | 28 days | The Engineer’s response | Time bar | 3.7.5 |
The defaults Gantt CSS starts from, editable per programme; check your contract.
JBCC and GCC 2015
Both forms are set up with their steps and registers. Their default periods in the app are still marked to confirm, so this guide gives no figures for them: enter the periods your contract and its special conditions set.
Periods to set from your contract
JBCC Principal Building Agreement
Set up with a notice of intention to claim, a claim with particulars once the delay can be quantified, and the Principal Agent’s decision. There is no early warning register. The default periods are in the app, marked to confirm, so set them from your contract.
Periods to set from your contract
GCC 2015
Set up with a claim with particulars (or a notice of intention first, with the particulars to follow), updated particulars while the event continues, a final claim, the Employer’s Agent’s ruling and a dispute notice if the ruling is not accepted. There is no early warning register. The default periods are in the app, marked to confirm, so set them from your contract.
From register to letter
Seven kinds of letter are drafted from the registers as Word documents, in our own plain wording: they name the clause from your set-up but never quote a contract form, and you edit each draft before it goes out. A weather register sets days lost against the contract’s allowance. When a claim needs the days worked out, the delay analysis guide explains the methods.