Notices, claims and time bars

How the Contract add-on counts the periods your contract sets, and what happens when one runs out.

Forms and registers

The registers are part of the Contract add-on. Choose the form in the contract set-up and the registers, the contract administrator’s title and the default rules follow from it.

The forms

  • JBCC Principal Building Agreement (Principal Agent)
  • GCC 2015 (Employer’s Agent)
  • NEC3 Engineering and Construction Contract (Project Manager)
  • NEC4 Engineering and Construction Contract (Project Manager)
  • FIDIC 1999 (Red and Yellow Books) (Engineer)
  • FIDIC 2017 (Red and Yellow Books) (Engineer)
  • Other forms (a general set of rules to adjust)

The registers

  • Early warnings

    Anything that could delay the works or add cost, raised early. Only for the forms that have an early warning procedure: not JBCC or GCC 2015.

  • Notices of delay

    The formal notices that keep the right to claim more time.

  • Compensation events

    Events at the employer’s risk that can change the price and the completion date.

  • EOT claims

    Extension of time claims: the days asked for, the days granted and the revised completion date.

How a step is counted

Each step in a register counts from something that happened: becoming aware of the event, its start or end, or another step being taken or falling due. The period runs in the unit the contract uses, and the rule says what a missed step means.

How a period is counted
UnitHow it counts
DaysCalendar days, every day counted.
Working daysDays that work on the contract’s calendar, which defaults to the programme’s own.
WeeksCalendar weeks of seven days.
Calendar days less holidaysCalendar days, skipping public holidays, proclaimed days and the builders’ break on the contract’s calendar.
MonthsCalendar months, ending on the same date of the month, or the month’s last day when it is shorter.
What happens when a step is late
ConsequenceWhat it means
Time barThe right is lost if the step is not taken in time. The register shows the entry as time-barred.
Deemed acceptedSilence counts as acceptance once the period runs out. The register shows the step as deemed.
Deemed refusedSilence counts as a refusal once the period runs out.
ReminderNothing is lost, but the step is shown as overdue so it can be chased.
  • A step shows as due soon 10 working days before its date by default; you can change that in the contract set-up.
  • Steps that repeat, such as monthly interim claims while an event continues, are listed once for each period.
  • Steps fall away when they no longer apply: a reminder to chase a reply once the reply is in, a dissatisfaction or dispute step once the claim is agreed.
  • The deadlines of every register go out as an iCalendar file, for Outlook, Google or Apple calendars.

Default periods

When you choose one of these forms, Gantt CSS fills in its rules. The main rules are below. Each one is a starting point, editable per programme.

Check your contract. These are the defaults Gantt CSS starts from, and you can edit every one per programme. Contracts are often amended by special conditions, so check yours. This guide is not legal advice.

NEC3 Engineering and Construction Contract

Set up with early warnings and compensation events: notification, reply, quotation, and acceptance when the Project Manager does not reply.

Default periods for NEC3 Engineering and Construction Contract
StepWhoPeriodCounted fromIf missedClause noted
Early warning givenContractorSame dayBecoming aware of the matterReminder16.1
Notify the compensation eventContractor8 weeksBecoming aware of the eventTime bar61.3
Reply to the notificationProject Manager1 weekThe notificationReminder61.4
Notification accepted if there is still no reply after the contractor points out the failureProject Manager2 weeksThe contractor’s notice of the failure to replyDeemed accepted61.4
Submit the quotationContractor3 weeksThe reply to the notificationReminder62.3
Reply to the quotationProject Manager2 weeksThe quotationReminder62.3
Quotation accepted if there is still no reply after the contractor points out the failureProject Manager2 weeksThe contractor’s notice of the failure to replyDeemed accepted62.6

The defaults Gantt CSS starts from, editable per programme; check your contract.

NEC4 Engineering and Construction Contract

The same compensation event steps as NEC3, with the early warning under its own clause.

Default periods for NEC4 Engineering and Construction Contract
StepWhoPeriodCounted fromIf missedClause noted
Early warning givenContractorSame dayBecoming aware of the matterReminder15.1
Notify the compensation eventContractor8 weeksBecoming aware of the eventTime bar61.3
Reply to the notificationProject Manager1 weekThe notificationReminder61.4
Notification accepted if there is still no reply after the contractor points out the failureProject Manager2 weeksThe contractor’s notice of the failure to replyDeemed accepted61.4
Submit the quotationContractor3 weeksThe reply to the notificationReminder62.3
Reply to the quotationProject Manager2 weeksThe quotationReminder62.3
Quotation accepted if there is still no reply after the contractor points out the failureProject Manager2 weeksThe contractor’s notice of the failure to replyDeemed accepted62.6

The defaults Gantt CSS starts from, editable per programme; check your contract.

FIDIC 1999 (Red and Yellow Books)

Set up with a notice of probable future events, the notice of claim, the detailed claim with interim and final claims, and the Engineer’s response.

Default periods for FIDIC 1999 (Red and Yellow Books)
StepWhoPeriodCounted fromIf missedClause noted
Notice of claimContractor28 daysBecoming aware of the eventTime bar20.1
Fully detailed claim (the first interim claim while the event continues)Contractor42 daysBecoming aware of the eventReminder20.1
Further interim claimsContractorEvery monthThe detailed claimReminder20.1
Final claimContractor28 daysThe end of the event’s effectsReminder20.1
Engineer’s responseEngineer42 daysThe detailed claimReminder20.1

The defaults Gantt CSS starts from, editable per programme; check your contract.

FIDIC 2017 (Red and Yellow Books)

Set up with advance warnings, the notice of claim, the detailed claim with interim and final claims, the Engineer’s agreement and determination, and a notice of dissatisfaction.

Default periods for FIDIC 2017 (Red and Yellow Books)
StepWhoPeriodCounted fromIf missedClause noted
Notice of claimContractor28 daysBecoming aware of the eventTime bar20.2.1
Engineer says the notice was late, or it stands as validEngineer14 daysThe notice of claimDeemed accepted20.2.2
Fully detailed claim (the first interim claim while the event continues)Contractor84 daysBecoming aware of the eventTime bar20.2.4
Further interim claimsContractorEvery monthThe detailed claimReminder20.2.6
Final claimContractor28 daysThe end of the event’s effectsReminder20.2.6
Engineer’s agreementEngineer42 daysThe detailed claimReminder3.7.3
Engineer’s determination, or the claim counts as rejectedEngineer42 daysThe end of the period for agreementDeemed refused3.7.3
Notice of dissatisfaction, if the claim is not agreedContractor28 daysThe Engineer’s responseTime bar3.7.5

The defaults Gantt CSS starts from, editable per programme; check your contract.

JBCC and GCC 2015

Both forms are set up with their steps and registers. Their default periods in the app are still marked to confirm, so this guide gives no figures for them: enter the periods your contract and its special conditions set.

  • Periods to set from your contract

    JBCC Principal Building Agreement

    Set up with a notice of intention to claim, a claim with particulars once the delay can be quantified, and the Principal Agent’s decision. There is no early warning register. The default periods are in the app, marked to confirm, so set them from your contract.

  • Periods to set from your contract

    GCC 2015

    Set up with a claim with particulars (or a notice of intention first, with the particulars to follow), updated particulars while the event continues, a final claim, the Employer’s Agent’s ruling and a dispute notice if the ruling is not accepted. There is no early warning register. The default periods are in the app, marked to confirm, so set them from your contract.

From register to letter

Seven kinds of letter are drafted from the registers as Word documents, in our own plain wording: they name the clause from your set-up but never quote a contract form, and you edit each draft before it goes out. A weather register sets days lost against the contract’s allowance. When a claim needs the days worked out, the delay analysis guide explains the methods.

Keep every time bar in view

The registers and their deadlines come with the Contract add-on, on top of Planning.